INSP-Final Inspection | 6/4/2018 | 6/5/2018 | 6/5/2018 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection for scope of work complete.
Please call 1/2 before arriving. Thanks Phone #: ###-#### Inspection requested via web by david davis
|
INSP-Final Inspection | 5/25/2018 | 5/29/2018 | 5/29/2018 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per point of contact, inspection request will be rescheduled for a later date.
Please call 1/2 hour before arriving. Thanks Phone #: ###-#### Inspection requested via web by david davis
|
INSP-Final Inspection | 7/11/2017 | 7/12/2017 | 7/12/2017 | P | PART |
Jim Page
|
|
|
Final inspection for deluge system complete, permit will remain in issued status until final BLD inspection is complete.
|
Meeting | | | 6/8/2017 | | DONE |
|
|
|
Met on site with Paul, Ron Johnson and several contractors involved in the project to discuss control requirements of the B50 and B51 link deluge systems. It was agreed that current code requiring listed releasing components and supervised service disconnects will be used.
|
1st review completed | | | 6/8/2017 | | PASS |
|
|
|
|
Alarm Plan Check | 6/8/2017 | | 6/8/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/8/2017 | | DONE |
|
|
|
Plans approved with review comments and requirements.
|
Permit Ready to Issue | | | 6/8/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/8/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/8/2017 | | 6/8/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 6/5/2017 | | 6/5/2017 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 6/5/2017 | | DONE |
|
|
|
Product data is missing. Informed Paul via email and Curtis via phone call.
|
Application received | | | 6/2/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 2 2017 8:10AM
|