INSP-Final Inspection | 3/26/2018 | 3/27/2018 | 3/27/2018 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
Todd Ketterling is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | FAIL |
Troy Cobbley
|
|
|
Was unable to test devices due to fire alarm permit issues. The forward flush test failed due to a lack of flow/pressure
|
INSP-Sprinkler Rough-in | 1/19/2018 | 1/19/2018 | 1/19/2018 | P | PASS |
Troy Cobbley
|
|
|
Piping above the lay-in ceilings is ok for cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2018 | 1/19/2018 | 1/19/2018 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed.
odd Ketterling is the contact for this overhead hydro. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 12/1/2017 | 12/4/2017 | 12/4/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 11/30/2017 | 12/1/2017 | 12/1/2017 | P | PASS |
Troy Cobbley
|
|
|
Piping above the hard lids is ok for cover. I noted electrical boxes located close to the pendants that may pose an obstruction problem.
|
INSP-Sprinkler Rough-in | 10/25/2017 | 10/26/2017 | 10/26/2017 | A | PASS |
Troy Cobbley
|
|
|
Overhead rough-in passed. Corrections have been made to the seismic bracing. No cover, except hardlids until the pendants/drops have been installed and verified.
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2017 | 10/24/2017 | 10/24/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line hydro passed. I also did a partial rough-in on just the overhead pipe, hangers and seismic bracing. Minor corrections are needed. No piping can be covered until corrections and all drops are installed and inspected.
|
Miscellaneous action | | | 10/24/2017 | | DONE |
|
|
|
Verify the addtional sprikler in the remote area. The hydraulics are still ok.
|
INSP-Sprinkler Rough-in | 8/23/2017 | 8/23/2017 | 8/23/2017 | P | PASS |
Troy Cobbley
|
|
|
Remaining underground supply piping from the IBR to the point of connection can be covered.
|
INSP-Sprinkler Rough-in | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for the underground, in building riser for building stub up approved for cover, remaining underground to be installed at a later date.
|
Sprinkler Plan Check | 6/22/2017 | | 6/22/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/22/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/22/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/22/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/22/2017 | | 6/22/2017 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 6/20/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/20/2017 | | 6/20/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/19/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2017 11:14AM
|