INSP-Final Inspection | 7/25/2017 | 7/25/2017 | 7/25/2017 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | FAIL |
Troy Cobbley
|
|
|
Permit can not be finaled due to ceiling tiles missing through-out project. Annual inspection on riser needs to be verified.
|
INSP-Sprinkler Rough-in | 7/14/2017 | 7/17/2017 | 7/17/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in area of work complete, approved for cover.
|
INSP-Sprinkler Rough-in | 6/29/2017 | 6/29/2017 | 6/29/2017 | P | DONE |
Troy Cobbley
|
|
|
Adam and I spoke about the two heads off of a single outlet. Hydraulic calculations will be required or piping will need to match plans.
|
Intake Approval | | | 6/20/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/20/2017 | | 6/20/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/20/2017 | | 6/20/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/20/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/20/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/20/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/20/2017 | | 6/20/2017 | | DONE |
Brittany Hill
|
|
|
|
Application received | | | 6/19/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2017 2:22PM
|