INSP-Final Inspection | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | FAIL |
Troy Cobbley
|
|
|
Forward flush passed, need backflow tagged, need pad at the PIV. Could not test devices due to fire alarm permit issued.
|
INSP-Sprinkler Rough-in/Hydro | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PART |
Troy Cobbley
|
|
|
The overhead hydro test passed. The sprinkler coverage for the east exterior canopy has been modified. There are two small shadowed areas that Todd Ketterling could not address with the materials/design provided. I spoke to Scott about it and he approved it. Sprinkler coverage still needs to be provided under the overhead door.
Todd Ketterling is the contact for this overhead hydro inspection for the admin. building. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/8/2018 | 1/9/2018 | 1/9/2018 | P | PART |
Troy Cobbley
|
|
|
Piping above the lay-in ceilings is ok to cover. Sprinkler coverage is required under the overhead door. Also the dry sidewall heads on under the east canopy are less than 4" from the underside of the soffit.
|
INSP-Supply line flush | 12/1/2017 | 12/4/2017 | 12/4/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 10/25/2017 | 10/26/2017 | 10/26/2017 | A | PASS |
Troy Cobbley
|
|
|
Overhead rough-in passed. Corrections have been made to the seismic bracing. No cover, except hardlids until the pendants/drops have been installed and verified.
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2017 | 10/24/2017 | 10/24/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line hydro passed. I also did a partial rough-in on just the overhead pipe, hangers and seismic bracing. Minor corrections are needed. Per Todd resubmittals are in the works. No piping can be covered until corrections, plan mods and all drops are installed and inspected.
Todd Ketterling Phone #: ###-####
|
Plan Modification Accepted | | | 10/20/2017 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 10/20/2017 | | 10/20/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/20/2017 | | 10/20/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/20/2017 | | DONE |
|
|
|
PLAN MOD
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 10/20/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/20/2017 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 8/4/2017 | 8/7/2017 | 8/7/2017 | A | PART |
Troy Cobbley
|
|
|
Rough to cover for 7'-0" from the building only. The remaining piping was not installed by Shilo. A separate permit will be required for this work from a licensed sprinkler contractor or Shilo will need to accept responcibility for this work. Shilo will need to resubmit plans for a change of scope. Plans need to be submitted showing the additional fittings in the underground supply line. Per Brian, the installer, the top of pipe is 5'-1" at the doorway/floor and is at 4'-9" at the connection. There is no sidewalk or land scaping just smooth travel from the door to the low point in the parking lot. If changes are made in the parking lot piping will need to be dug up and modified to the correct depth.
|
Permit Ready to Issue | | | 7/11/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/11/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/11/2017 | | 7/11/2017 | | DONE |
Candy A. Nichols
|
|
|
|
Miscellaneous action | | | 7/10/2017 | | DONE |
|
|
|
The Fire Marshal approved the FDC location based on client request.
|
Sprinkler Plan Check | 7/10/2017 | | 7/10/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/6/2017 | | 7/6/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/6/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 6/21/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/21/2017 | | 6/21/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/21/2017 | | 6/21/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/21/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/21/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 6/19/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2017 3:04PM
|