Permit Information
Permit NumberFIR17-00308
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 1820 N MOCKBEE PL
Project NamePuopolo Residence
Customer Number 
ePlanReviewYes
Description
[Puopolo Residence]
The fire sprinkler scope of work consists of protecting a two level single family dwelling with a combination domestic and passive purge sprinkler system. The piping in the attic will be tented. Residential sprinklers are used throughout.

[BLD17-00636]
Permit for the construction of a new 3,056 sq. ft., two story (first story 1,223 sq. ft., second story 1,833 sq. ft.) single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 380 sq. ft. of covered patio/porch and a 953 sq. ft. attached garage per the approved plans, and any notations. R-1B zoning and setbacks per planning. **DAF**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/20/201710/20/201710/20/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete.
Fees Due Hold10/19/201710/19/201710/19/2017 PASS
Details
INSP-Final Inspection10/17/201710/18/201710/18/2017PFAIL
DetailsJim Page
Flow switch would not activate on waterflow.
INSP-Final Inspection10/13/201710/13/201710/13/2017PCANC
DetailsJim Page
Final inspection request will be rescheduled for a later date per conversation with Jake, phone number ###-####.
INSP-Final Inspection10/4/201710/6/201710/6/2017AFAIL
DetailsJim Page
Isolation valve for fire sprinkler system is required per fire sprinkler permit review.
INSP-Sprinkler Rough-in7/18/20177/19/20177/19/2017PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover.
INSP-Sprinkler Rough-in7/17/20177/18/20177/18/2017AFAIL
DetailsJim Page
Multiple area's where piping is exposed to attic space, piping not covered with plastic sheeting, pocket will not be maintained between sheetrock and fire sprinkler piping, cover is not approved.
INSP-Sprinkler Rough-in/Hydro7/9/20177/10/20177/10/2017PPART
DetailsJim Page
Hydrostatic test complete for overhead fire sprinkler piping. Rough in inspection for overhead fire sprinkler piping complete, piping between conditioned area's approved for cover, fire sprinkler piping located in attic spaces cannot be covered until insulation/tenting has been installed over the top of the fire sprinkler piping and tenting passed inspection.
INSP-Sprinkler Rough-in/Hydro7/6/20177/6/20177/6/2017PFAIL
DetailsJim Page
Fire sprinkler dead needs to be added or relocated to cover under stairs as shown on approved drawings. Fire sprinkler head in the southeast bedroom needs to be relocated to cover shadow area above closet area.
INSP-Sprinkler Rough-in/Hydro6/30/20177/6/20177/6/2017ACANC
DetailsJim Page
Please call Jake when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
Issue and Print Permit  6/23/2017 DONE
Inspection Record Card- Fire6/23/2017 6/23/2017 DONE
DetailsTisha Gallop
Intake Approval  6/22/2017 PASS
Plan assigned to (Tim)6/22/2017 6/22/2017 DONE
DetailsTim Frost
Sprinkler Plan Check6/22/2017 6/22/2017 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  6/22/2017 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  6/22/2017 DONE
DetailsTim Frost
Application received  6/20/2017 DONE
Application submitted via PDS Online on Jun 20 2017 12:47PM