INSP-Final Inspection | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Overhead hydro test passed. Placards are on order.
Todd Ketterling is the contact for this hydro. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2018 | 3/29/2018 | 3/29/2018 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled.
Todd Ketterling is the contact for this Hydro. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 3/26/2018 | 3/27/2018 | 3/27/2018 | A | PART |
Troy Cobbley
|
|
|
Installation for the most part is ok. One four way brace at the top of Stair #2 is missing as well as flexible cplgs through a CMU wall. The position of the hose valves in Stair #1 need to be relocated (swung) as per conversation away from the roof drain line as well as possible drainage concerns. It appears the FDC and drain out of the west side of the building interferes with the stairwell door and will need to be relocated.
Todd Ketterling is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Sprinkler Plan Check | 7/5/2017 | | 7/5/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/5/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/5/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/5/2017 | | 7/5/2017 | | DONE |
Brittany Hill
|
|
|
|
Sprinkler Plan Check | 6/27/2017 | | 6/27/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/27/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/27/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 6/26/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/26/2017 | | 6/26/2017 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/26/2017 | | DONE |
|
|
|
Spoke with the Fire Marshal and asked him if he wanted the manual standpipes interconnected. He said NO since there may be two different crews training at the same time.
|
Application received | | | 6/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 20 2017 1:22PM
|