INSP-Final Inspection | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Jon Beazer is the contact for this final inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 5/9/2018 | 5/14/2018 | 5/14/2018 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for levels 2 through 5 complete, level 1 to be completed at a later date. Fire sprinkler heads in bike storage area on level 1 will need to have the insulation raised so it's not resting on the uprights or pendant heads will need to be installed before level 1 final.
Jon Beazer is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/16/2018 | 4/16/2018 | 4/16/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining overhead fire sprinkler piping in garage complete, approved for cover. Rough to cover inspection for overhead fire sprinkler piping in trash shoot room complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/13/2018 | 4/16/2018 | 4/16/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed for level 1 wet system and wet standpipe (Combo floor supply/standpipe has been completed) complete, no pressure loss observed at riser provided gauge.
|
INSP-Sprinkler Rough-in | 3/29/2018 | 3/30/2018 | 3/30/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids in elevator lobby/common area level 1 complete, approved for cover.
|
INSP-Sprinkler Rough-in | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping abover remaining hardlids in parking area complete, parking area approved for cover. Hardlids in common area level 1 approved for cover with exception to elevator lobby, elevator lobby to be inspected at a later date.
|
INSP-Sprinkler Rough-in/Hydro | 3/20/2018 | 3/21/2018 | 3/21/2018 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for levels 2, 3, 4 and 5 overhead fire sprinkler piping as well as wet standpipe/floor supply for sprinklers witnessed, no pressure loss observed at contractor provided gauge at main riser. Level 1 and 6 inch wet standpipe to have hydrostatic test dome at a later date.
|
INSP-Sprinkler Rough-in | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above hardlids on the east and south side of parking area complete, north side common area hardlids are complete, areas mentioned/inspected approved for cover. RTS-O sensors will need to be installed in the area around space heaters above parking garage hardlid to monitor temperature in case of heater failure, area above parking garage hardlids needs to be maintained at 40 degrees or higher at all times.
|
INSP-Conference | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | DONE |
Jim Page
|
|
|
Combustible concealed space around rooftop heater/fire place on the northeast side patio will either need to be made into a non-combustible space with sheetrock, space needs to be filled with non-combustible insulation or a fire sprinkler head will need to be added for proper fire sprinkler coverage.
|
INSP-Sprinkler Rough-in | 1/11/2018 | 1/12/2018 | 1/12/2018 | A | PART |
Scott Arellano
|
|
|
Rough-in inspection of NW rooms and corridor. 2nd floor sprinkler plans. OK to cover.
|
INSP-Sprinkler Rough-in | 1/4/2018 | 1/5/2018 | 1/5/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for level 2 overhead fire sprinkler piping complete (3rd floor from ground level), level 2 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/21/2017 | 12/22/2017 | 12/22/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for level 3 overhead fire sprinkler piping complete (4th floor from ground level), level 3 approved for cover.
|
INSP-Sprinkler Rough-in | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PART |
Jim Page
|
|
|
Partial rough to ocver inspection complete, notated the city approved drawings with yellow highlighter/red ink area's approved for cover.
|
INSP-Sprinkler Rough-in | 9/12/2017 | 9/13/2017 | 9/13/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads Level 3 Area 3 complete, Level 3 Area 3 approved for cover, city approved planes are notated with yellow highlighter area's that were inspected.
|
INSP-Sprinkler Rough-in | 8/21/2017 | 8/22/2017 | 8/22/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping on level 2 complete (first level of apartments above parking level) Notated the city approved drawings with green highlighter/red ink area's approved for cover. Concealed combustible spaces highlighted in rough to cover area cannot be completely covered until area's are verified to be sheetrocked and made into a non-combustile concealed space (area's also marked with green highlighter and red ink on city approved sprinkler drawings with associated notes written on drawings)
|
Sprinkler Plan Check | 8/8/2017 | | 8/8/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/8/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/8/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/8/2017 | | 8/8/2017 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 8/8/2017 | | 8/8/2017 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 8/2/2017 | | DONE |
|
|
|
Spoke with Kyle with Shiloh Fire Sprinkler. Informed Kyle that the Fire Marshal has determined that the combustible concealed spaces will need to be protected by fire sprinklers; or each concealed space will need to be constructed with a single layer of 5/8 type X sheet rock with tape and joint compound; or completely filled with non combustible insulation.
|
Telephone call | | | 8/1/2017 | | DONE |
|
|
|
Received telephone call from Kyle with Shiloh Fire Sprinkler inquiring about status of request to exclude sprinklers in combustible concealed spaces. Informed Kyle that the request has been forwarded to the Assitant Fire Marshal for review.
|
Telephone call | | | 8/1/2017 | | DONE |
|
|
|
Left message with Assitant Fire Marshal regarding request from Shiloh.
|
Telephone call | | | 7/31/2017 | | DONE |
Scott Arellano
|
|
|
Spoke with Kyle regarding additional information pertaining to correction item #6 in the plan review report. Instructed Kyle to submit this information for review so we can evaluated the designers proposal.
|
Miscellaneous action | | | 7/31/2017 | | DONE |
|
|
|
Forwarded additinal information to Assistant Fire Marshal for review of request to exclude sprinkler protection in combustible concealed spaces; as per pipe chase exception.
|
Sprinkler Plan Check | 7/14/2017 | | 7/14/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/14/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Meeting | | | 7/7/2017 | | DONE |
|
|
|
Per discussion with the assistant fire marshal a standpipe outlet for the roof top garden is NOT required.
|
Sprinkler Plan Check | 6/30/2017 | | 6/30/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/30/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/30/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 6/27/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/27/2017 | | 6/27/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/21/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 21 2017 3:24PM
|