INSP-Final Inspection | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | PASS |
Jim Page
|
|
|
FDC is no longer blocked, final fire sprinkler inspection complete.
|
INSP-Final Inspection | 12/8/2017 | 12/11/2017 | 12/11/2017 | A | FAIL |
Jim Page
|
|
|
FDC is blocked by air conditioner condensor.
|
INSP-Sprinkler Rough-in/Hydro | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | DONE |
Troy Cobbley
|
|
|
Overhead hydro test complete
|
INSP-Supply line flush | 12/7/2017 | 12/8/2017 | 12/8/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Supply line flush | 12/1/2017 | 12/5/2017 | 12/5/2017 | A | FAIL |
Troy Cobbley
|
|
|
not ready
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 10/3/2017 | 10/4/2017 | 10/4/2017 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 9/27/2017 | 9/28/2017 | 9/28/2017 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered except for tie in area
|
INSP-Sprinkler Rough-in | 9/20/2017 | 9/21/2017 | 9/21/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping can be buried.
|
Permit Ready to Issue | | | 6/27/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/27/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/27/2017 | | 6/27/2017 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Intake Approval | | | 6/26/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/26/2017 | | 6/26/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/26/2017 | | 6/26/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/26/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 22 2017 12:21PM
|