INSP-Final Inspection | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Supply line flush | 1/24/2018 | 1/24/2018 | 1/24/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in | 11/6/2017 | 11/7/2017 | 11/7/2017 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. .Piping can be covered.
|
INSP-Sprinkler Rough-in | 10/3/2017 | 10/4/2017 | 10/4/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground Inspection passed. Supply piping can be covered.
|
Sprinkler Plan Check | 7/12/2017 | | 7/12/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/12/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/12/2017 | | 7/12/2017 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 7/11/2017 | | 7/11/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/11/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 7/5/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 7/5/2017 | | 7/5/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 30 2017 8:34AM
|