INSP-Final Inspection | 10/30/2017 | 10/31/2017 | 10/31/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Plan Modification Accepted | | | 10/30/2017 | | DONE |
|
|
|
Started Plan Mod work flow for Steven Urbanczyk to upload per his request.
|
INSP-Final Inspection | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | FAIL |
Troy Cobbley
|
|
|
All devices tested and passed. Need plan modifications and NFPA record of completion forms when plans are approved.
|
INSP-Final Inspection | 10/20/2017 | 10/24/2017 | 10/24/2017 | P | FAIL |
Troy Cobbley
|
|
|
Today I was only able to verify strobe placement. See the city approved plans for locations where strobes are overspaced, too high or needing to be added. As-built needed prior to a final sign off. Small documents are missing. Data sheets are missing. No sprinkler interconnections have been pre-tested.
|
Permit Ready to Issue | | | 7/13/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/13/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/13/2017 | | 7/13/2017 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (Lee) | 7/10/2017 | | 7/10/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 7/10/2017 | | PASS |
|
|
|
|
Alarm Plan Check | 7/10/2017 | | 7/10/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/10/2017 | | DONE |
|
|
|
Plans approved with review comments.
|
Application received | | | 7/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 5 2017 1:18PM
|