INSP-Final Inspection | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Sprinkler Rough-in | 11/29/2017 | 11/29/2017 | 11/29/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids complete, hardlids approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2017 | 11/6/2017 | 11/6/2017 | P | PASS |
Jim Page
|
|
|
Underground supply hydrostatc test complete.
|
Sprinkler Plan Check | 9/19/2017 | | 9/19/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/19/2017 | | DONE |
|
|
|
all met
|
Issue and Print Permit | | | 9/19/2017 | | DONE |
|
|
|
|
Intake Approval | | | 8/15/2017 | | |
|
|
|
|
Plan assigned to (Tim) | 8/15/2017 | | 8/15/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/15/2017 | | 8/15/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/15/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/15/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 8/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 11 2017 4:55PM
|