INSP-Final Inspection | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | DONE |
Jim Page
|
|
|
Overhead hydrostatic test was witnessed on 9MAR2018, wrong permit was requested on day of inspection request.
|
INSP-Supply line flush | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | DONE |
Jim Page
|
|
|
Undergorund main line flush complete.
|
INSP-Sprinkler Rough-in | 1/10/2018 | 1/11/2018 | 1/11/2018 | A | PASS |
Troy Cobbley
|
|
|
Tenting has been repaired and piping can be covered.
|
INSP-Sprinkler Rough-in | 1/10/2018 | 1/10/2018 | 1/10/2018 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed but the tenting has issues. Piping can not be covered until the tenting has been re-inspected.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
Issue and Print Permit | | | 8/23/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/23/2017 | | 8/23/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 8/22/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/22/2017 | | 8/22/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/22/2017 | | 8/22/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/22/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/22/2017 | | DONE |
|
|
|
|
Application received | | | 8/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 17 2017 1:03PM
|