INSP-Final Inspection | 4/11/2018 | 4/12/2018 | 4/12/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Call 30 minutes prior to arrival Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 4/10/2018 | 4/11/2018 | 4/11/2018 | A | CANC |
Troy Cobbley
|
|
|
The project related fire alarm permit has not been scheduled.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Final Inspection | 4/5/2018 | 4/6/2018 | 4/6/2018 | P | CANC |
Troy Cobbley
|
|
|
Unable to test the sprinkler devices due to fire alarm issues. Contractor needs to verify that the shipping clips have been removed from heads.
|
INSP-Sprinkler Rough-in/Hydro | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Supply line flush | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | DONE |
Jim Page
|
|
|
Undergorund main line flush complete.
|
INSP-Sprinkler Rough-in | 1/5/2018 | 1/8/2018 | 1/8/2018 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 11/16/2017 | 11/17/2017 | 11/17/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
Issue and Print Permit | | | 8/23/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/23/2017 | | 8/23/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 8/22/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/22/2017 | | 8/22/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/22/2017 | | 8/22/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/22/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/22/2017 | | DONE |
|
|
|
|
Application received | | | 8/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 17 2017 1:08PM
|