INSP-Final Inspection | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 5/30/2018 | 6/4/2018 | 6/4/2018 | P | CANC |
Jim Page
|
|
|
Could not complete final for fire sprinklers due to fire alarm issues. Final inspection will be rescheduled for a later date.
Mike Bierman is the contact for this final inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2018 | 5/22/2018 | 5/22/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping on system 5 complete witnessed, no pressure loss observed at riser proveded gauge.
Mike Bierman is the contact for this inspection. If he is not able to be reached, call Jon Beazer at ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 4/16/2018 | 4/16/2018 | 4/16/2018 | P | DONE |
Jim Page
|
|
|
Fire sprinkler conference complete.
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2018 | 1/23/2018 | 1/23/2018 | A | PASS |
Troy Cobbley
|
|
|
Todays inspection was just overhead hydro test for wet systems 1, 2, 3 and 4. The all passed.
|
Sprinkler Plan Check | 8/28/2017 | | 8/28/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/28/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/28/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/28/2017 | | 8/28/2017 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/23/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/23/2017 | | 8/23/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/21/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 21 2017 10:09AM
|