Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR17-00542
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 1424 W FRONT ST
Project NameVerraso Downtown
Customer Number 
ePlanReviewYes
Description
[Verraso Downtown]
Install underground sprinkler piping, including Post Indicator Valve, for new 8-plex

[BLD17-01499]
Permit for the construction of an 8 unit, 2 story wood-framed apartment building with work to include general site work and construction of the new building per the approved plans. Special inspections required for structural steel AISC360, Concrete Construction Post installed anchors, and soils.This building is fire sprinklered with an NFPA-13R system. JAR
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/13/20188/13/20188/13/2018APASS
DetailsJim Page
Final inspection complete.
INSP-Sprinkler Rough-in/Hydro8/10/20188/10/20188/10/2018APASS
DetailsJim Page
Final underground supply inspection complete.
INSP-Supply line flush11/20/201711/22/201711/22/2017ADONE
DetailsJim Page
Underground supply flush complete.
INSP-Sprinkler Rough-in/Hydro11/17/201711/20/201711/20/2017APASS
DetailsJim Page
Underground supply hydrostatic test complete
INSP-Sprinkler Rough-in9/25/20179/25/20179/25/2017PPASS
DetailsJim Page
Underground supply rough to cover inspection complete, approved for cover.
INSP-Supply line flush9/25/20179/25/20179/25/2017PCANC
DetailsJim Page
Underground Hydro Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in9/22/20179/22/20179/22/2017PCANC
DetailsJim Page
Underground supply not ready to inspect, inspection request will be reschedule for a later date, this request is cancelled.
INSP-Supply line flush9/22/20179/22/20179/22/2017PCANC
DetailsJim Page
Underground Rough-In Phone #: ###-#### Inspection requested via web by Connie Danes
Issue and Print Permit  9/21/2017 DONE
Sprinkler Plan Check9/20/2017 9/20/2017 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  9/20/2017 DONE
DetailsTim Frost
Permit Ready to Issue  9/20/2017 DONE
All requirements met
Intake Approval  9/18/2017 PASS
Plan assigned to (Tim)9/18/2017 9/18/2017 DONE
DetailsTim Frost
Sprinkler Plan Check9/18/2017 9/18/2017 FAIL
DetailsTim Frost
1st review completed  9/18/2017 FAIL
DetailsTim Frost
Application received  9/14/2017 DONE
Application submitted via PDS Online on Sep 14 2017 3:44PM