INSP-Final Inspection | 8/13/2018 | 8/13/2018 | 8/13/2018 | A | PASS |
Jim Page
|
|
|
Final inspection complete.
|
INSP-Sprinkler Rough-in/Hydro | 8/10/2018 | 8/10/2018 | 8/10/2018 | A | PASS |
Jim Page
|
|
|
Final underground supply inspection complete.
|
INSP-Supply line flush | 11/20/2017 | 11/22/2017 | 11/22/2017 | A | DONE |
Jim Page
|
|
|
Underground supply flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 11/17/2017 | 11/20/2017 | 11/20/2017 | A | PASS |
Jim Page
|
|
|
Underground supply hydrostatic test complete
|
INSP-Sprinkler Rough-in | 9/25/2017 | 9/25/2017 | 9/25/2017 | P | PASS |
Jim Page
|
|
|
Underground supply rough to cover inspection complete, approved for cover.
|
INSP-Supply line flush | 9/25/2017 | 9/25/2017 | 9/25/2017 | P | CANC |
Jim Page
|
|
|
Underground Hydro Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | CANC |
Jim Page
|
|
|
Underground supply not ready to inspect, inspection request will be reschedule for a later date, this request is cancelled.
|
INSP-Supply line flush | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | CANC |
Jim Page
|
|
|
Underground Rough-In Phone #: ###-#### Inspection requested via web by Connie Danes
|
Issue and Print Permit | | | 9/21/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/20/2017 | | 9/20/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/20/2017 | | DONE |
|
|
|
All requirements met
|
Intake Approval | | | 9/18/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 9/18/2017 | | 9/18/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/18/2017 | | 9/18/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 9/18/2017 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 9/14/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 14 2017 3:44PM
|