INSP-Final Inspection | 11/8/2017 | 11/9/2017 | 11/9/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The fire alarm plans address was incorrect. Address has been changed to match the building address
|
Telephone call | | | 11/7/2017 | | DONE |
|
|
|
Jeremy Berg called to say that one of the new duct detectors shown on the most recent plan modification is shown in the wrong place and a different product than originally thought. I told him that he could supply as built drawings to show the correct location and model numbers / product data. As long as there aren't other changes, no resubmittal will be required.
|
Miscellaneous action | | | 11/6/2017 | | DONE |
|
|
|
Kenny requested work flow be opened to upload design changes that include 2 added duct smoke detectors.
|
Plan Modification Accepted | | | 11/6/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 11/6/2017 | | 11/6/2017 | | DONE |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/6/2017 | | DONE |
|
|
|
Plan modification approved. No additional review comments.
|
Permit Ready to Issue | | | 11/6/2017 | | DONE |
|
|
|
PLEASE DO NOT RE ISSUE
|
Issue and Print Permit | | | 11/6/2017 | | DONE |
|
|
|
|
INSP-Final Inspection | 10/30/2017 | 11/1/2017 | 11/1/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Jeremy Phone #: ###-####
|
(F) Reprint permit | | | 10/30/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/30/2017 | | DONE |
|
|
|
|
INSP-Final Inspection | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for final due to the PIV not reporting correctly and I noted alot of the notofication devices are overspaced and the area behind the front counter has no coverage. No actual testing performed. I went over items with the tech. Plans are too small to read and do not show the communication means being used. As-builts or possibly plan modifications are needed.
Jeremy Berg Phone #: ###-####
|
Miscellaneous action | | | 10/27/2017 | | DONE |
|
|
|
Kenny requested workflow be opened for required changes to notification found during inspection.
|
Plan Modification Accepted | | | 10/27/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 10/27/2017 | | 10/27/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/27/2017 | | DONE |
|
|
|
Plan modification approved. No additional review comments.
|
Permit Ready to Issue | | | 10/27/2017 | | DONE |
|
|
|
Plan Mod Approved, DO NOT REISSUE
|
Telephone call | | | 10/25/2017 | | DONE |
|
|
|
Mike called to say that the owner has decided to remove the sprinkler monitoring system provided by Apex and replace it by one provided by Peak. Also, they want to change from an alarm dialer to a cellular communicator. Mike requested the work flow be opened to upload a plan modification for the new communicator.
|
Plan Modification Accepted | | | 10/25/2017 | | DONE |
|
|
|
Changed dialer to cell communicator.
|
Alarm Plan Check | 10/25/2017 | | 10/25/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/25/2017 | | DONE |
|
|
|
Plan mod approved. No additional review comments.
|
Permit Ready to Issue | | | 10/25/2017 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 10/25/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/25/2017 | | DONE |
|
|
|
|
1st review completed | | | 9/29/2017 | | FAIL |
|
|
|
See 1st review comments.
|
Plan resubmittals received | | | 9/29/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 9/29/2017 | | 9/29/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/29/2017 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 9/29/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/29/2017 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 9/28/2017 | | 9/28/2017 | | DONE |
Lee G Meredith
|
|
|
|
Application received | | | 9/27/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2017 4:01PM
|