INSP-Final Inspection | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/14/2018 | 3/15/2018 | 3/15/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price Inspection cancelled via mobile web on Thursday, March 15, 2018.
|
Plan Modification Accepted | | | 3/15/2018 | | DONE |
|
|
|
Change Telguard communicator to Honeywell.
|
Alarm Plan Check | 3/15/2018 | | 3/15/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/15/2018 | | DONE |
|
|
|
Plan modification approved. No additional review comments.
|
Permit Ready to Issue | | | 3/15/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/15/2018 | | DONE |
|
|
|
|
INSP-Final Inspection | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need dedicated circuit for the dialer, need plan mod for the dialer that is being used, need the modified candella for the Womens Restroom shown on the plan mods. No devices tested.
Call prior to going Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
Plan Modification Accepted | | | 3/12/2018 | | CANC |
|
|
|
modification workflow started per request from customer // cancelled plan mod workflow (was in applicant upload status) per phone call from Sean Stone 3/12/18 4:45pm leg
|
CHANGE STATUS TO (ISS) | | | 3/12/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 1/29/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 1/29/2018 | | 1/29/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/29/2018 | | DONE |
|
|
|
Plan modification approved. No additional review comments.
|
Permit Ready to Issue | | | 1/29/2018 | | DONE |
|
|
|
Plan Mod approved,
DO NOT REISSUE
|
Telephone call | | | 1/26/2018 | | DONE |
|
|
|
Sean requested the work flow be opened for uploads. Dialer is being changed to a cellular communicator and requires a plan modification.
|
Plan resubmittals received | | | 10/6/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 10/6/2017 | | 10/6/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/6/2017 | | DONE |
|
|
|
Plans approved with review comments and drawing notes.
|
Permit Ready to Issue | | | 10/6/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/6/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/4/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 10/4/2017 | | 10/4/2017 | | FAIL |
Lee G Meredith
|
|
|
See 1st review comments.
|
Plan assigned to (Lee) | 10/2/2017 | | 10/2/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 10/2/2017 | | FAIL |
|
|
|
Failed prescreen review and returned for corrections. Errors on FA-1 and FA-2 rotation is wrong. Several rooms have visible notification spacing wrong. Email to Adam informing him of required corrections.
|
Application received | | | 9/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 29 2017 4:08PM
|