Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR17-00593
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 10481 W FAIRVIEW AVE
Project Name17-136 Belmont Plaza - TI
Customer Number 
ePlanReviewYes
Description
[Vector Church]
The fire sprinkler scope of work consists of changing all sprinklers in the space to quick response type per IFC requirements.

• The building shell is under permit BLD17-01449

[BLD17-03023]
The fire sprinkler system is used for unlimited area of the building AND to allow 3-hr fire barrier walls in lieu of fire walls. The fire sprinkler system is NOT allowed to be used for building area increase for A Occupancies. To do tenant improvement work inside a 12,633 square foot tenant space for a new church. This tenant space was created under shell permit BLD17-01449. Work is to include a coffee bar, coffee preparation equipment, a gypsum board soffit, interior nonbearing walls, interior doors, a shear wall at the edge of an existing mezzanine where a portion of the mezzanine was removed, structural upgrades to the remaining mezzanine diaphragm in the adjacent space, suspended acoustical ceiling, millwork, and finishes. A new 30.67 foot wide opening and a new 6.33 foot wide opening will be created in an existing interior masonry bearing wall. Work is to include expanded concrete footings, steel columns, steel beam, and steel headers and jambs. Special Inspection is required for anchors post-installed in hardened concrete and for welding. Some building shell work was done under permit BLD17-01449. Work included structural modifications to the roof (beams and joists) to support new roof top HVAC equipment, new openings in the North exterior masonry bearing wall with a new 2-hr steel beam or lintel supported by new 2-hr steel columns or jambs and expanded concrete footings, new storefront glazing and entrance doors, 3-hr fire barrier walls per the 2012 IEBC in lieu of fire walls to create separate buildings, 3-hr exit doors in the fire barrier wall, interior nonbearing walls, and 2 toilet rooms accessible to the disabled. Modular stage, modular ramp, modular sound room, and modular stairways, are deferred submittal items and are required to be reviewed and approved before installation. This permit is intended to establish a Certificate of Occupancy for this tenant. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/25/20181/26/20181/26/2018APASS
DetailsTroy Cobbley
Permit finaled
Plan Modification Accepted  1/25/2018 DONE
Plan assigned to (Tim)1/25/2018 1/25/2018 DONE
DetailsTim Frost
Sprinkler Plan Check1/25/2018 1/25/2018 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  1/25/2018 DONE
CHANGE STATUS TO (ISS)  1/25/2018 DONE
Plan Mod no fee per Tim F. see documents
(F) Reprint permit  1/25/2018 DONE
INSP-Sprinkler Rough-in1/5/20181/5/20181/5/2018APASS
DetailsTroy Cobbley
Rough-in passed
Sprinkler Plan Check12/28/2017 12/28/2017 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  12/28/2017 DONE
DetailsTim Frost
Permit Ready to Issue  12/28/2017 DONE
Met
Issue and Print Permit  12/28/2017 DONE
Sprinkler Plan Check12/26/2017 12/26/2017 FAIL
DetailsTim Frost
Miscellaneous action  12/26/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Sprinkler Plan Check12/11/2017 12/11/2017 FAIL
DetailsTim Frost
Miscellaneous action  12/11/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Telephone call  12/11/2017 DONE
I have spoken to Don and Trent in regards to the following matter. I have sent several email.

In the last review I asked them to arrange a conference at my office to discuss the project.

The problem:
Phoenix Fire Protection is adding a backflow preventer to a large strip mall. The have provide calculations for several tenant spaces. However, they have not supplied calculations for the tenant space whic is farthest from the supply. They do NOT have work in this area. However, the backflow preventer effects the water supply which effects the hydraulic calculation in the most remote area. Per NFPA addiontal calculations are required. I cannot get Phoenix Fire Protection to submit these calculations.
Sprinkler Plan Check11/22/2017 11/22/2017 FAIL
DetailsTim Frost
Miscellaneous action  11/22/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Sprinkler Plan Check11/1/2017 11/1/2017 FAIL
DetailsTim Frost
Miscellaneous action  11/1/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Sprinkler Plan Check10/26/2017 10/26/2017 FAIL
DetailsTim Frost
Miscellaneous action  10/26/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Sprinkler Plan Check10/20/2017 10/20/2017 FAIL
DetailsTim Frost
1st review completed  10/20/2017 FAIL
DetailsTim Frost
Miscellaneous action  10/20/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  10/19/2017 PASS
Plan assigned to (Tim)10/19/2017 10/19/2017 DONE
DetailsTim Frost
Application received  10/6/2017 DONE
Application submitted via PDS Online on Oct 6 2017 9:42AM