Permit Information
Permit NumberFIR17-00596
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 8800 W EMERALD ST
Project NameTV Hosp - Tenant Improvement
Customer Number 
ePlanReviewYes
Description
[Treasure Valley Hospital - Tenant Improvement]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

• The underground piping is under permit FIR17-00302

[BLD17-00596]
To complete Package A of a project to construct a 13,921 square foot addition to connect an existing 44,000 square foot hospital to an existing 13,500 square foot office building (about 1,500 square feet of the existing 15,000 square foot office building will be demolished to facilitate the addition). A 3-hr fire wall will be constructed to separate the Type I-B construction (about 57,921 square feet) from the Type V-B construction (about 13,500 square feet). This is a 2 package project. This permit is for concrete footings, concrete foundations, concrete slabs on grade, steel columns, steel beams, steel roof joists, steel roof deck, and a 3-hr masonry fire wall/smoke barrier wall. The building shell and interior tenant improvement work will be completed under future Package B. Special Inspection is required for soils, concrete, masonry, steel (including welding and bolting), and anchors post installed in hardened concrete. The design for the structural steel connections, exterior curtain walls, and steel stud connections to the structure are deferred submittal items. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The submitted interior architectural drawings are for reference only and have not been approved. This permit does not establish a Certificate of Occupancy for any portion of the addition. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**

Alternative Materials and Methods:

• There are no AMM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/19/20187/20/20187/20/2018APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in7/12/20187/13/20187/13/2018APASS
DetailsTroy Cobbley
The remaining piping can be covered.
INSP-Sprinkler Rough-in7/12/20187/12/20187/12/2018PPASS
DetailsTroy Cobbley
Piping in the Office near the Sterile Corridor can be covered.

Contact Hunter Anderson ###-#### 30 min prior to RTC Insp Start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in7/10/20187/11/20187/11/2018APASS
DetailsTroy Cobbley
See the city approved plans for additional areas that are approved for cover.

Contact Hunter Anderson - ###-#### 30 min prior to RTC insp Start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in7/6/20187/9/20187/9/2018APASS
DetailsTroy Cobbley
See the city approved plans for room locations where overhead piping can be covered.
INSP-Sprinkler Rough-in5/25/20185/25/20185/25/2018PPART
DetailsJim Page
Rough to cover inspection for fire sprinkler piping located in operating room 1, OR room 1 is notated on the city approved drawings and is approved for cover (total of 4 heads).

Contact Leroy Anderson - ###-#### 30 Min Prior to RTC Insp Start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in5/24/20185/25/20185/25/2018ACANC
DetailsJim Page
Contact Leroy Anderson ###-#### 30 Min Prior to RTC Insp start , please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Sprinkler Rough-in4/2/20184/2/20184/2/2018PPASS
DetailsTroy Cobbley
The fire sprinkler work in the Office, as discussed, is complete.

Contact Jon Olmstead - ###-#### 30 min prior to RTC insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in3/22/20183/23/20183/23/2018APASS
DetailsTroy Cobbley
See the city approved plans for the two rooms where the rough-in has passed and piping can be covered. They are an Office and Vending.
INSP-Sprinkler Rough-in3/15/20183/16/20183/16/2018APASS
DetailsTroy Cobbley
Work complete in Passage 115
INSP-Sprinkler Rough-in3/14/20183/15/20183/15/2018AFAIL
DetailsTroy Cobbley
Ceiling tile has not been installed in Passage 115


Contact Jon Olmstead ###-#### 30 min prior to RTC Start please Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in3/13/20183/14/20183/14/2018APASS
DetailsTroy Cobbley
See the city approved plans for location where the piping can be covered in Passage 115.

Contact Jon Olmstead - ###-#### 30 min prior to Rough-In start please Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in3/12/20183/13/20183/13/2018AFAIL
DetailsTroy Cobbley
No city approved drawings on site. No inspection performed. I also noted missing fire proofing.
Sprinkler Plan Check10/19/2017 10/19/2017 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  10/19/2017 DONE
DetailsTim Frost
Permit Ready to Issue  10/19/2017 DONE
All Met
Issue and Print Permit  10/19/2017 DONE
Intake Approval  10/10/2017 PASS
Plan assigned to (Tim)10/10/2017 10/10/2017 DONE
DetailsTim Frost
Sprinkler Plan Check10/10/2017 10/10/2017 FAIL
DetailsTim Frost
Please, see attached comments.
1st review completed  10/10/2017 FAIL
DetailsTim Frost
Miscellaneous action  10/10/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  10/9/2017 DONE
Application submitted via PDS Online on Oct 9 2017 9:09AM