INSP-Final Inspection | 8/10/2018 | 8/13/2018 | 8/13/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Jordan Fuger is the contact for this inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/26/2018 | 6/26/2018 | 6/26/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply witnessed, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/21/2017 | 11/22/2017 | 11/22/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
Intake Approval | | | 10/12/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/12/2017 | | 10/12/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/12/2017 | | 10/12/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/12/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/12/2017 | | DONE |
|
|
|
all met
|
Issue and Print Permit | | | 10/12/2017 | | DONE |
|
|
|
|
Application received | | | 10/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 11 2017 2:11PM
|