INSP-Final Inspection | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
|
INSP-Sprinkler Rough-in | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PASS |
Jim Page
|
|
|
Rough to ocver inspection for area of work complete.
|
INSP-Sprinkler Rough-in | 11/29/2017 | 11/29/2017 | 11/29/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for phase 1 area complete, area being called phase 1 approved for cover.
|
Intake Approval | | | 10/17/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/17/2017 | | 10/17/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/17/2017 | | 10/17/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/17/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/17/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/17/2017 | | DONE |
|
|
|
all met
|
Issue and Print Permit | | | 10/17/2017 | | DONE |
|
|
|
|
Application received | | | 10/16/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 16 2017 3:22PM
|