INSP-Final Inspection | 11/29/2017 | 11/29/2017 | 11/29/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 11/8/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
Troy Phone #: ###-####
|
INSP-Supply line flush | 11/2/2017 | 11/3/2017 | 11/3/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line fluch passed. Jeff got 3psi out of the 4" flushing outlet
|
INSP-Supply line flush | 11/1/2017 | 11/2/2017 | 11/2/2017 | P | CANC |
Troy Cobbley
|
|
|
CALL LONNIE w/TVFP. NEED THIS UNDERGROUND FLUSHED Phone #: ###-#### >> Inspection requested via web by Brad Bettencourt Inspection cancelled from web by: Brad Bettencourt
|
INSP-Sprinkler Rough-in | 11/1/2017 | 11/2/2017 | 11/2/2017 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | PASS |
Troy Cobbley
|
|
|
Cover inspection at South Bore is passed and can be covered. This is from the Suez point of connection to Big Mike the locomotive.
|
INSP-Sprinkler Rough-in | 10/23/2017 | 10/24/2017 | 10/24/2017 | P | PART |
Troy Cobbley
|
|
|
Cover inspection for partial underground passed. See the city approved plans for location of piping that is ok for cover. Today was for riser to the tee.
|
Issue and Print Permit | | | 10/23/2017 | | DONE |
|
|
|
|
Application received | | | 10/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 20 2017 12:47PM
|
Intake Approval | | | 10/20/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/20/2017 | | 10/20/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/20/2017 | | 10/20/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/20/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2017 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/20/2017 | | DONE |
|
|
|
Spoke to the assitant fire marshall. He is ok with the new 8" line feeding the existing hydrant and the existing sprinkler system since this an exsiting condition.
|
Miscellaneous action | | | 10/20/2017 | | DONE |
|
|
|
Spoke with Jeff Packham at Treasure Valley Fire Protection . Explained to him his company would have to be responsible for the new 8" underground fire service line per Idaho State Requirments. He aggreed.
|
Permit Ready to Issue | | | 10/20/2017 | | DONE |
|
|
|
all met
|