INSP-Final Inspection | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection complete.
|
INSP-Final Inspection | 6/13/2018 | 6/14/2018 | 6/14/2018 | P | CANC |
Jim Page
|
|
|
Inspection could no be performed due to fire alarm panel issues. Inspection request will need to be rescheduled, this request is cancelled.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/21/2018 | 3/21/2018 | 3/21/2018 | P | DONE |
Jim Page
|
|
|
Underground hydrostatic test witnessed, no pressure loss observed at contractor provided supply gauge.
|
INSP-Sprinkler Rough-in/Hydro | 3/21/2018 | 3/21/2018 | 3/21/2018 | A | FAIL |
Jim Page
|
|
|
Undergound supply lost 7 PSI during hydro, underground will have to be re-tested.
|
INSP-Sprinkler Rough-in/Hydro | 1/18/2018 | 1/18/2018 | 1/19/2018 | P | PASS |
Scott Arellano
|
|
|
ung ok to cover.
|
Issue and Print Permit | | | 12/1/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/1/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/30/2017 | | 11/30/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/30/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/30/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/26/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/26/2017 | | 10/26/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/26/2017 | | 10/26/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 10/26/2017 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 10/25/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 25 2017 2:23PM
|