INSP-Final Inspection | 1/30/2018 | 1/31/2018 | 2/1/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/24/2018 | 1/26/2018 | 1/26/2018 | A | FAIL |
Troy Cobbley
|
|
|
Contact the plan reviewer for guidance on wether a plan modification is needed or if as-builts will suffice.The one line riser does not match actual points and descriptions such as dry system pressure switch, AES instead of phone lines....ect. Also per dicussion with on site electrician, hvac and general contractor not all of the duct smoke detectors are functional I stated that all devices, as shown on the plans, need to be installed/cunctional/tested or plans will need to be modified to delete the devices. The deleted devices will require a separate permit when installed prior to an occupancy approval for the individual tenants. Today we tested all devices except the flow switch for system #2 and the duct smoke detectors.
This is for Belmont Core Phone #: ###-#### Inspection requested via web by Ken Webster
|
Plan resubmittals received | | | 11/13/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 11/13/2017 | | 11/13/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/13/2017 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 11/13/2017 | | DONE |
|
|
|
All Met
|
Issue and Print Permit | | | 11/13/2017 | | DONE |
|
|
|
|
Miscellaneous action | | | 11/8/2017 | | DONE |
|
|
|
Received engineer's review letter directly from ECI that approves the originally submitted drawings dated 7-10-17. This has been inserted into the eplan review documents.
|
Miscellaneous action | | | 11/6/2017 | | DONE |
|
|
|
Received email from Ken including new drawings. Still no review letter from the engineer of record. Responded to ken letting him know this is still needed and that he will need to upload drawings to start the next review.
|
Application received | | | 10/26/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 26 2017 9:03AM
|
Plan assigned to (Lee) | 10/26/2017 | | 10/26/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 10/26/2017 | | FAIL |
|
|
|
Failed pre-screen review. Needs engineer of record review.
|