INSP-Final Inspection | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Gary Gambino
|
Miscellaneous action | | | 8/3/2018 | | DONE |
|
|
|
Record drawings received and approved. Uploaded into eplanreview.
|
INSP-Final Inspection | 8/1/2018 | 8/2/2018 | 8/2/2018 | A | CANC |
Troy Cobbley
|
|
|
As-builts have not been provided to plan review yet.
Phone #: ###-#### Inspection requested via web by Gary Gambino
|
INSP-Final Inspection | 7/12/2018 | 7/13/2018 | 7/13/2018 | P | PART |
Troy Cobbley
|
|
|
Temporary being given until as-builts submitted/approved showing the address changes, deleting PIV and deleting tamper at the knox box.
Phone #: ###-#### Inspection requested via web by Gary Gambino
|
INSP-Final Inspection | 7/10/2018 | 7/12/2018 | 7/12/2018 | P | FAIL |
Troy Cobbley
|
|
|
See city approved plans for audio/visual devices that are overspaced. Voice evac message is not functional in the new area or the existing gym. Tamper switches wired backwards. Devices are missing. Inspection stopped until all corrections have been made and system has been pre-tested.
Phone #: ###-#### Inspection requested via web by Gary Gambino
|
Plan assigned to (Lee) | 11/21/2017 | | 11/21/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 11/21/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 11/21/2017 | | 11/21/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/21/2017 | | DONE |
|
|
|
Plans approved with review comments and requirements noted on drawings.
|
Permit Ready to Issue | | | 11/21/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/21/2017 | | DONE |
|
|
|
|
Application received | | | 11/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 20 2017 2:46PM
|