INSP-Final Inspection | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Final Inspection | 6/13/2018 | 6/14/2018 | 6/14/2018 | P | CANC |
Jim Page
|
|
|
Inspection could no be performed due to fire alarm panel issues. Inspection request will need to be rescheduled, this request is cancelled.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2018 | 6/4/2018 | 6/4/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauges.
Richard Clark is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | CANC |
Jim Page
|
|
|
Charles Lamb is the contact for this rough to cover -- hydro inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2018 | 5/30/2018 | 5/30/2018 | P | CANC |
Jim Page
|
|
|
Charles Lamb is the contact for this rough to cover -- hydro inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/29/2018 | 5/29/2018 | 5/29/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in the butcher area and the bakery area complete, approved for cover.
|
INSP-Sprinkler Rough-in | 5/29/2018 | 5/30/2018 | 5/29/2018 | P | CANC |
Jim Page
|
|
|
Charles Lamb is the contact for this rough to cover and hydro inspection. Thank you for your help. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 4/25/2018 | 4/26/2018 | 4/26/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, all hardlids approved for cover, fire sprinkler heads that will be installed in drop in tile ceiling will need to be inspected before cover is approved.
|
INSP-Sprinkler Rough-in/Hydro | 3/15/2018 | 3/21/2018 | 3/21/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler above hardlids on mezzanine level complete, notated city approved drawings with green highlighter/red ink area approved for cover.
|
INSP-Supply line flush | 3/15/2018 | 3/21/2018 | 3/21/2018 | P | CANC |
Jim Page
|
|
|
Gabe Garduno is the contact for this flush. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|
Sprinkler Plan Check | 12/21/2017 | | 12/21/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/21/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/21/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/21/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/15/2017 | | 12/15/2017 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
|
Miscellaneous action | | | 12/15/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 11/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 22 2017 11:12AM
|
Intake Approval | | | 11/22/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/22/2017 | | 11/22/2017 | | DONE |
Tim Frost
|
|
|
|