INSP-Final Inspection | 8/14/2018 | 8/15/2018 | 8/15/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Jordan Fuger is the contact for this Final inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | FAIL |
Troy Cobbley
|
|
|
Could not test the interconnect with the fire alarm system. Forward flush passed.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 8/10/2018 | 8/13/2018 | 8/13/2018 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm inspection was not ready, need canopies on 401's, need pressure relief valves installed, need verification for painted concealed canopies, need to pass the forward flush.....inspection stopped.
Jordan Fuger is the contact for this final inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 8/3/2018 | 8/7/2018 | 8/7/2018 | A | CANC |
Jim Page
|
|
|
Fire alarms are not ready per conversation with point of contact, inspection request will be rescheduled to coincide with fire alarm inspection, this request is cancelled.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/26/2018 | 7/26/2018 | 7/26/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/26/2018 | 7/26/2018 | 7/26/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauges.
Richard Clark is the contact for this overhead hydro inspection. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 5/22/2018 | 5/24/2018 | 5/24/2018 | P | DONE |
Jim Page
|
|
|
Undergorund main line flush complete.
Jordan Fuger is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/17/2018 | 5/18/2018 | 5/18/2018 | P | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete, rough in inspection for overhead fire sprinkler piping above hardlids complete, hardlids approved for cover. Notated city approved drawings where sway brace corrections are required.
The phone number provided is for Tom with CM Company. Our foreman on site is Troy, but he does not have a cell phone at the moment. Our office number is ###-#### if you have questions. Thank you! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/8/2018 | 3/9/2018 | 3/9/2018 | A | CANC |
Jim Page
|
|
|
Jordan is the contact for this hydro. Thank you. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Supply line flush | 3/8/2018 | 3/9/2018 | 3/9/2018 | P | CANC |
Troy Cobbley
|
|
|
Jordan is the contact for this flush. Thank you. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
Issue and Print Permit | | | 12/7/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/6/2017 | | 12/6/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/6/2017 | | DONE |
|
|
|
|
Miscellaneous action | | | 12/4/2017 | | PEND |
|
|
|
Asked fire marshal if protection should be required below raised floor per NFPA requirements.
|
Sprinkler Plan Check | 11/30/2017 | | 11/30/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 11/30/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/30/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 11/29/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/29/2017 | | 11/29/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 11/28/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 28 2017 3:45PM
|