INSP-Final Inspection | 12/22/2017 | 12/26/2017 | 12/26/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete
|
INSP-Sprinkler Rough-in | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Jim Page
|
|
|
Rouh to cover inspection for area of work complete, approved for cover. In tenant space there are two different types of heads in the same area, Viking Standard response GB 155 degree and Reliable Model G heads, model G heads need to be changed to glass bulb Viking heads. Head change will be verified at final inspection.
|
INSP-Final Inspection | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | CANC |
Jim Page
|
|
|
Tenant space not ready for final inspection, this inspection request is going to be changed to a rough in inspection.
|
Sprinkler Plan Check | 12/8/2017 | | 12/8/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/8/2017 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 12/8/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/1/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/1/2017 | | 12/1/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/1/2017 | | 12/1/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 12/1/2017 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 11/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 30 2017 3:10PM
|