INSP-Final Inspection | 2/28/2018 | 2/28/2018 | 2/28/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Final Inspection | 2/26/2018 | 2/26/2018 | 2/26/2018 | P | CANC |
Troy Cobbley
|
|
|
Cancel per the general contractor.
FRY Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Sprinkler Rough-in/Hydro | 2/22/2018 | 2/22/2018 | 2/22/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
|
INSP-Supply line flush | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply witnessed, no pressure loss observed at fire riser gauge.
|
INSP-Sprinkler Rough-in | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply and remote FDC complete, approved for cover.
|
INSP-Conference | 2/12/2018 | 2/13/2018 | 2/13/2018 | A | DONE |
Jim Page
|
|
|
Fire conference complete.
|
INSP-Sprinkler Rough-in | 2/1/2018 | 2/1/2018 | 2/1/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above grid ceiling areas in kitchen and main dining area complete, kitchen and main dining area approved for cover.
|
INSP-Sprinkler Rough-in | 1/8/2018 | 1/9/2018 | 1/9/2018 | A | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping on level 1 level and mezzanine level on level 1 complete.
|
Sprinkler Plan Check | 12/13/2017 | | 12/13/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/13/2017 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 12/13/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/13/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/6/2017 | | 12/6/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 12/6/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/6/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 12/5/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/5/2017 | | 12/5/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 12/4/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 4 2017 4:05PM
|