Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR17-00720
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 850 W FRONT ST
Project NameBOISE CENTER PHASE 7
Customer Number 
ePlanReviewYes
Description
[Boise Convention Center - 1st Floor] - Quick Permit
ATTACH TO AN EXISTING 3" MAIN AND RELOCATED AND SPACE SPRINKLERS TO FIT THE NEW LAY-IN TILE CEILING.

[BLD17-03709]
The fire sprinkler system is used for fire area. Permit is to remodel 2,082 sq. ft. of existing men’s and women’s restrooms and entry lobby/ballroom work on the main floor of the existing building. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select interior walls, removal of interior finishes, removal of select door/door frames, removal of select counters, removal of plumbing fixtures and accessories, removal of select gypsum ceiling and select soffits, construction of select interior non-bearing walls, select wall infill, select new door/door frame, new accessible restrooms for the disabled, new plumbing fixtures and accessories, select new acoustic ceiling, relocated and new light fixtures, lowering an existing lobby suspended acoustic ceiling, select new soffits, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/26/20181/26/20181/26/2018APASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.
INSP-Sprinkler Rough-in1/16/20181/17/20181/17/2018APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Issue and Print Permit  12/13/2017 DONE
Intake Approval  12/11/2017 PASS
Plan assigned to (Tim)12/11/2017 12/11/2017 DONE
DetailsTim Frost
Sprinkler Plan Check12/11/2017 12/11/2017 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  12/11/2017 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  12/11/2017 DONE
DetailsTim Frost
Permit Ready to Issue  12/11/2017 DONE
Met
Application received  12/8/2017 DONE
Application submitted via PDS Online on Dec 8 2017 4:49PM