INSP-Final Inspection | 1/9/2018 | 1/9/2018 | 1/9/2018 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply and remote FDC complete.
|
INSP-Sprinkler Rough-in/Hydro | 1/9/2018 | 1/9/2018 | 1/9/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply and remote FDC witnessed, no observed pressure loss at riser gauge.
|
INSP-Sprinkler Rough-in | 1/8/2018 | 1/8/2018 | 1/8/2018 | P | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled for 9JAN2018, this request is cancelled.
|
INSP-Supply line flush | 12/21/2017 | 12/22/2017 | 12/22/2017 | A | DONE |
Jim Page
|
|
|
Underground supply flush complete.
|
INSP-Supply line flush | 12/20/2017 | 12/21/2017 | 12/21/2017 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Brian Phone #: ###-####. To be rescheduled
|
INSP-Sprinkler Rough-in | 12/13/2017 | 12/14/2017 | 12/14/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground, remote FDC and remote main drain complete, approved for cover.
|
Intake Approval | | | 12/13/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/13/2017 | | 12/13/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/13/2017 | | 12/13/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/13/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2017 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/13/2017 | | DONE |
|
|
|
Project was delayed waiting on contractor to submit data sheets.
|
Permit Ready to Issue | | | 12/13/2017 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 12/13/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/13/2017 | | DONE |
|
|
|
|
Application received | | | 12/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 11 2017 11:20AM
|