INSP-Final Inspection | 3/30/2018 | 4/2/2018 | 4/2/2018 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
after 10am please // Zach Phone #: ###-####
|
INSP-Final Inspection | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | FAIL |
Troy Cobbley
|
|
|
There were issues with the interconnection of the pressure switches and tamper switches. No actual testing was performed.
Zach Phone #: ###-####
|
Alarm Plan Check | 3/23/2018 | | 3/23/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/23/2018 | | DONE |
|
|
|
Plan modification approved with review comments.
|
Permit Ready to Issue | | | 3/23/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 3/23/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 3/22/2018 | | DONE |
|
|
|
Solenoid model number is not on the approved product list. Emailed John to have him submit the correct product data. John confirmed with the manufacturer the solenoid model is approved and provided backup documentation from the manufacturer.
|
INSP-Final Inspection | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PART |
Troy Cobbley
|
|
|
The sync'ing of the notification has been repaired/tested and passed. All manual pull stations have been tested, the smoke detector above the main facp has been tested.
Zack Phone #: ###-####
|
INSP-Final Inspection | 3/14/2018 | 3/15/2018 | 3/15/2018 | A | FAIL |
Jim Page
|
|
|
Flow switches on wet system fire sprinkler risers worked correctly. Audio visual notification did not sync correctly, audio visual devices will need to be re-inspected.
|
INSP-Final Inspection | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PART |
Troy Cobbley
|
|
|
For todays inspection I verifed the elevator recall smoke and heat detectors and the single duct smoke detector in the basement. The rest of the time I spoke to Steve, the project superintendant, about the possibility for a temporary.
Zak Anderson - Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
Permit Ready to Issue | | | 3/12/2018 | | DONE |
|
|
|
Plan Mod approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 3/12/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 3/9/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 3/9/2018 | | 3/9/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/9/2018 | | DONE |
|
|
|
Plan Modification for addition of preaction in server room approved. No additional review comments. This approval is dependant upon sprinkler review and approval of added pre-action system.
|
Miscellaneous action | | | 3/8/2018 | | DONE |
|
|
|
Workflow reopened so John can upload pre-action system changes in a plan mod.
|
INSP-Final Inspection | 2/28/2018 | 3/1/2018 | 3/1/2018 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was a walk through. I verified the head end equipment. I noted that plans need to be resubmitted for a plan modification due to 14 guage wire being used where as 12 guage was submitted. Also there are additional notification devices needed and many devices that need to be relocated or candella increased. The second floor wall layout at the east end does not match the plans. There is an access controled egress lock on the second floor that will need connected to the fire alarm system or contact will need to be made to the building code official. No devices have been tested.
John Howard - Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
Miscellaneous action | | | 2/28/2018 | | DONE |
|
|
|
As built drawings received. Due to the extent of changes, I emailed John to let him know that a resubmittal would be required. Also, I need documentation on the solenoid and relay that shows they are listed for the use and a solenoid service switch needs to be added.
|
INSP-Conference | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | DONE |
Troy Cobbley
|
|
|
We dicussed strobe modifications in the first floor lobby and in the basement.
John Phone #: ###-####
|
Issue and Print Permit | | | 12/18/2017 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 12/14/2017 | | 12/14/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 12/14/2017 | | PASS |
|
|
|
|
Alarm Plan Check | 12/14/2017 | | 12/14/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/14/2017 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 12/14/2017 | | DONE |
|
|
|
|
Application received | | | 12/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 13 2017 9:35AM
|