INSP-Sprinkler Rough-in/Hydro | 1/24/2018 | 1/25/2018 | 1/25/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for newly installed overhead fire sprinkler piping witnessed, no pressure loss observed at contractor provided gauge.
|
INSP-Sprinkler Rough-in/Hydro | 1/23/2018 | 1/24/2018 | 1/24/2018 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed due to a leaking coupling
Nate Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/17/2018 | 1/18/2018 | 1/18/2018 | A | PART |
Troy Cobbley
|
|
|
Rough-in for the most part is ok. Tim approved the 1/2" heads being used. Will need sprinkler coverage under both stairs since the areas are being used for storage. Also possibly need coverage under the coveyor since it is also being used for storage. A hydro test wil also be needed as discussed.
Nate Phone #: ###-####
|
Intake Approval | | | 12/15/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/15/2017 | | 12/15/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/15/2017 | | 12/15/2017 | | DEFR |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/15/2017 | | DEFR |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/15/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Issue and Print Permit | | | 12/15/2017 | | DONE |
|
|
|
|
Application received | | | 12/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 13 2017 7:50PM
|