INSP-Final Inspection | 3/16/2018 | 3/16/2018 | 3/16/2018 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection complete.
|
CHANGE STATUS TO (ISS) | | | 3/15/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 3/13/2018 | | DONE |
|
|
|
Reopened at Sean's request so a cellular communicator could be added.
|
Plan Modification Accepted | | | 3/13/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 3/13/2018 | | 3/13/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/13/2018 | | DONE |
|
|
|
Plan modification to change dialer to cell communicator approved. No additional review comments.
|
Permit Ready to Issue | | | 3/13/2018 | | DONE |
|
|
|
DO NO RE ISSUE. Plan Mod
|
Telephone call | | | 1/9/2018 | | DONE |
|
|
|
Adam Bayne called to say that there had been a double interlock suppression system in the building that had been taken out prior to their permit application that they were not aware of. Also, the system is being converted to a single interlock system. Existing smoke detection had been removed by the demo crew without a permit and new walls have been installed, possibly without a permit. Adam wanted to know if the single interlock system would be acceptable, although not required. I told him to discuss this with Tim Frost.
|
Issue and Print Permit | | | 12/19/2017 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 12/18/2017 | | 12/18/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 12/18/2017 | | PASS |
|
|
|
|
Alarm Plan Check | 12/18/2017 | | 12/18/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/18/2017 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 12/18/2017 | | DONE |
|
|
|
Met
|
Application received | | | 12/15/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 15 2017 3:31PM
|