Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR17-00768
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7500 W MOSSY CUP ST
Project NameNxEdge Exterior Addition
Customer Number 
ePlanReviewYes
Description
[NxEdge Exterior Addition]
The fire sprinkler scope of work consists of installing an addition to the existing dry fire sprinkler system in this existing building to cover the new exterior mechanical room being added on.

[BLD17-03441]
The fire sprinkler system is used for building area increase, for story increase, to allow the H-3 Occupancy, and for fire area. Permit to construct a new 900 sq. ft. semi-heated attached pre-engineered metal building addition on the east side of the existing building. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select equipment for new structure, the construction of a new manufactured steel building, new unit heater, new light fixtures, electrical work, plumbing work and mechanical work. Note: special inspection required see attached form #310. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/15/20181/17/20181/17/2018PPASS
DetailsTroy Cobbley
Permit finaled

Call Anthony before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro1/4/20181/5/20181/5/2018APASS
DetailsTroy Cobbley
The overhead rough-in and hydro test passed for the new addition. Contractor will add the branchline restraints before next inspection as discussed.

Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
Sprinkler Plan Check12/28/2017 12/28/2017 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  12/28/2017 DONE
DetailsTim Frost
Permit Ready to Issue  12/28/2017 DONE
DetailsChristina Prado
All requirements met
Issue and Print Permit  12/28/2017 DONE
Intake Approval  12/27/2017 PASS
Plan assigned to (Tim)12/27/2017 12/27/2017 DONE
DetailsTim Frost
Sprinkler Plan Check12/27/2017 12/27/2017 FAIL
DetailsTim Frost
1st review completed  12/27/2017 FAIL
DetailsTim Frost
Miscellaneous action  12/27/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  12/26/2017 DONE
Application submitted via PDS Online on Dec 26 2017 3:06PM