Permit Information
Permit NumberFIR17-00774
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 8000 S FEDERAL WAY
Project NameMicron BLDG51 30-1
Customer Number 
ePlanReviewYes
Description
[Micron Building 51 - System 30-1 - C24074]
The fire sprinkler scope of work consists of a system designed as a 4”x4”x 2½” grid. The system is
designed based on OH II for 3000 ft² per IFC for Semiconductor H5.
• The underground is under permit FIR16-00701
• See addendum for graphic scope of work
[BLD16-03440]
For the construction of a new one story building with a basement for a fabrication and R&D facility to
include related site work. The building includes a 157,037 sq. ft. basement, a 170,997 sq. ft. first story
and a 33,638 sq. ft. equipment platform. This building is fully fire sprinklered and alarmed for H
occupancy. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/12/20198/13/20198/13/2019APASS
DetailsJim Page
Final fire sprinkler inspection for scope of work has been completed. Sprinkler head under added ductwork that was outside scope of work will need to be added before life fire safety final, a seperate permit will be required for obstruction coverage.

CLarence Phone #: ###-####
INSP-Sprinkler Rough-in8/13/20198/13/20198/13/2019APASS
DetailsJim Page
Rough in inpsection for this system has been completed.
INSP-Sprinkler Rough-in/Hydro8/13/20198/13/20198/13/2019ADONE
DetailsJim Page
Hydrostatic test for this system has been witnessed, no pressure loss was observed.
Fees Due Hold4/13/2018 12/27/2018 DONE
DetailsTisha Gallop
Fees Due Hold2/28/2018 4/12/2018 DONE
DetailsChristina Prado
This needs paid do not override
Fees Due Hold1/9/2018 2/27/2018 DONE
DetailsBrittany Hill
Sprinkler Plan Check1/8/2018 1/8/2018 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  1/8/2018 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  1/8/2018 DONE
DetailsTim Frost
Permit Ready to Issue  1/8/2018 DONE
Issue and Print Permit  1/8/2018 DONE
Intake Approval  1/5/2018 PASS
Plan assigned to (Tim)1/5/2018 1/5/2018 DONE
DetailsTim Frost
Application received  12/28/2017 DONE
Application submitted via PDS Online on Dec 28 2017 3:28PM