Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR17-00776
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 11343 W PRESIDENT DR
Project NameInnovative Air T.I.
Customer Number 
ePlanReviewYes
Description
[Innovative Air TI]
The fire sprinkler scope of work consists of a new tenant in an existing warehouse building. The existing two dry systems will be converted into two wet systems. The existing sprinkler system has been re-calculated based on the new rack storage arrangement.

Location on Plan - Warehouse
Commodity - HVAC , Unit Heaters in wood boxes
Classification - III
Storage Type (rack, solid pile, etc.) - Racks (Single, Double Row)
Pallet Type (wood or plastic) - Wood
Aisle Width - 8’
Height of Storage - 20’
Ceiling Height - 41’
Encapsulated - No
Solid Shelves - No
Smoke and Heat Vents - No
Draft Curtain - Yes (Not required but existing)
In Rack Sprinklers - No
Sprinkler Type - ELO-231 SIN TY5111
High Temperature Sprinklers Required - Yes
Applicable NFPA Section - T 16.2.1.3.2, F 16.2.1.3.2(c) Curve F,
F 16.2.1.3.4.1
Hydraulic Design Criterion - .42/2000
Hose Stream Requirements - 500


• Racking permit BLD17-04659 (Not reviewed at the time of this fire sprinkler review.)
[BLD17-04612]
Tenant Improvement of an existing Type II-B Sprinkled prefabricated metal building to warehouse and office space with a second floor addition within the office space area. Improvements include but are not limited to new window and door fenestration in the existing building, new exterior paint and metal and wood siding on the north elevation, new non-combustible interior wall framing and structural floor framing of steel and concrete pan deck for new second floor, restroom, office, conference, storage and break room areas, new mechanical, plumbing and electrical, modifications to the existing fire sprinkler and alarm system. Additional exterior improvements would include a paving overlay of the existing parking area, re-stripe and new landscape features.

Fire Protection Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/7/20183/9/20183/9/2018PPASS
DetailsTroy Cobbley
Permit finaled
Plan Modification Accepted  1/26/2018 DONE
Sprinkler Plan Check1/26/2018 1/26/2018 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  1/26/2018 DONE
Plan assigned to (Tim)1/26/2018 1/26/2018 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  1/26/2018 DONE
CHANGE STATUS TO (ISS)  1/26/2018 DONE
Plan Mod approved, Per Tim F no charge
Sprinkler Plan Check1/9/2018 1/9/2018 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  1/9/2018 DONE
DetailsTim Frost
Permit Ready to Issue  1/9/2018 DONE
Issue and Print Permit  1/9/2018 DONE
Intake Approval  1/2/2018 PASS
Plan assigned to (Tim)1/2/2018 1/2/2018 DONE
DetailsTim Frost
Sprinkler Plan Check1/2/2018 1/2/2018 FAIL
DetailsTim Frost
1st review completed  1/2/2018 FAIL
DetailsTim Frost
Miscellaneous action  1/2/2018 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  12/29/2017 DONE
Application submitted via PDS Online on Dec 29 2017 10:47AM