INSP-Final Inspection | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/26/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed for Units 101, 102, 201, 202, 301 and 302 except no tenting has been done yet and none of the sidewall sprinklers have been installed yet. No piping can be covered yet.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/26/2018 | 6/27/2018 | 6/26/2018 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2018 | 6/20/2018 | 6/20/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok for cover.
Bryan Collins is the contact for this underground rough-in. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Sprinkler Plan Check | 1/12/2018 | | 1/12/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/12/2018 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 1/12/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/5/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/5/2018 | | 1/5/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/5/2018 | | 1/5/2018 | | FAIL |
Tim Frost
|
|
|
Prescreen
|
Application received | | | 1/4/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 4 2018 4:38PM
|