INSP-Final Inspection | 4/10/2018 | 4/12/2018 | 4/12/2018 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection for scope of work complete.
|
INSP-Final Inspection | 2/9/2018 | 2/9/2018 | 2/9/2018 | A | PART |
Jim Page
|
|
|
Fire alarm notification complete, fire sprinkler riser monitoring complete, elevator recall complete, remaining item to test is the elevator shunt.
|
INSP-Alarm Testing | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | DONE |
Jim Page
|
|
|
FIre alarm testing complete.
|
Miscellaneous action | | | 2/6/2018 | | DONE |
|
|
|
Shane emailed to request workflow be opened for resubmittal.
|
Plan Modification Accepted | | | 2/6/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 2/6/2018 | | 2/6/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/6/2018 | | DONE |
|
|
|
Plan modification approved with additional review comments.
|
Permit Ready to Issue | | | 2/6/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 2/6/2018 | | DONE |
|
|
|
Plan Mod Approved
|
(F) Reprint permit | | | 2/6/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/22/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 1/19/2018 | | DONE |
|
|
|
Failed prescreen review due to all drawings combined as one. Shane resubmitted seperated drawings.
|
Plan assigned to (Lee) | 1/19/2018 | | 1/19/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 1/19/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 1/19/2018 | | 1/19/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/19/2018 | | DONE |
|
|
|
Plans approved, as noted, with review comments.
|
Permit Ready to Issue | | | 1/19/2018 | | DONE |
|
|
|
|
Application received | | | 1/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 18 2018 10:40AM
|