INSP-Final Inspection | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2018 | 3/5/2018 | 3/5/2018 | P | PASS |
Troy Cobbley
|
|
|
overhead hydro test passed
Mark Jensen is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2018 | 3/2/2018 | 3/2/2018 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to visible loss of pressure on the guage.
Mark Jensen is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | CANC |
Troy Cobbley
|
|
|
Mark Jensen is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/23/2018 | 2/26/2018 | 2/26/2018 | P | PASS |
Troy Cobbley
|
|
|
Remaining piping ok to cover. Need longitudinal earthquake bracing in two locations
Mark Jensen is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | PASS |
Troy Cobbley
|
|
|
The piping above the two hardlids, as marked on the plans, is ok to cover.
|
Intake Approval | | | 1/23/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/23/2018 | | 1/23/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/23/2018 | | 1/23/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 1/23/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/23/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/23/2018 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 1/23/2018 | | DONE |
|
|
|
|
Application received | | | 1/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 19 2018 1:33PM
|