INSP-Final Inspection | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PASS |
Jim Page
|
|
|
Freezer has been removed, final fire sprinkler inspection for area of work complete.
Rick Fry Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Final Inspection | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for scope of work complete. A walk in freezer is located inside of the cooler, walk in freezer does not have fire sprinklers installed, freezer may possibly be removed, FIR permit for fire sprinklers cannot be finaled until freezer has sprinklers installed or until the freezer is removed.
|
INSP-Sprinkler Rough-in | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping in scope of work complete.
|
Intake Approval | | | 2/5/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/5/2018 | | 2/5/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/5/2018 | | 2/5/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/5/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2018 | | DONE |
Tim Frost
|
|
|
|
Override - Parcel Holds | | | 2/5/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 2/5/2018 | | DONE |
|
|
|
Met
|
Override - Parcel Holds | | | 2/5/2018 | | |
|
|
|
|
Issue and Print Permit | | | 2/5/2018 | | DONE |
|
|
|
|
Application received | | | 1/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 31 2018 8:21AM
|