INSP-Final Inspection | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete for area of work.
|
INSP-Sprinkler Rough-in | 3/26/2018 | 3/27/2018 | 3/27/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler in area of work complete, area of work approved for cover.
|
INSP-Sprinkler Rough-in | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler located above hardlid in conference room complete, conference room hardlid approved for cover.
|
Issue and Print Permit | | | 2/7/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/2/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/2/2018 | | 2/2/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/2/2018 | | 2/2/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/2/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/2/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/2/2018 | | DONE |
|
|
|
met
|
Application received | | | 1/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 31 2018 9:26AM
|