INSP-Final Inspection | 6/29/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Reschedule final per Troy''s request. Phone #: ###-#### Inspection requested via web by Laura Tyson
|
INSP-Final Inspection | 4/27/2018 | 4/30/2018 | 4/30/2018 | A | FAIL |
Troy Cobbley
|
|
|
The hydro test on the FDC piping failed.
|
(F) Reprint permit | | | 2/2/2018 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 2/1/2018 | | 2/1/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/1/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 2/1/2018 | | 2/1/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/1/2018 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 2/1/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/1/2018 | | DONE |
|
|
|
|
Application received | | | 1/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 31 2018 1:58PM
|