INSP-Final Inspection | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection for area of work complete.
Contact is Sean. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Miscellaneous action | | | 3/26/2018 | | DONE |
|
|
|
Received drawings for riser and voltage calculations that show the correct wire gauge.
|
Alarm Plan Check | 2/28/2018 | | 2/28/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/28/2018 | | DONE |
|
|
|
Plans approved as noted with revised review comments.
|
Permit Ready to Issue | | | 2/28/2018 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 2/28/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/27/2018 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 2/2/2018 | | 2/2/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/2/2018 | | FAIL |
|
|
|
Missing product data, PE review approval and several common areas are missing visible notification. Morgan notified via email.
|
Application received | | | 2/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 1 2018 12:39PM
|