INSP-Final Inspection | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection complete.
|
INSP-Final Inspection | 3/8/2018 | 3/9/2018 | 3/9/2018 | A | FAIL |
Troy Cobbley
|
|
|
Arrived at the project at 7:45am and met contractor but we found that the police department was not there for access. I was unable to come back later in the day due to inspection load and no availability of the fire alarm contractor. No inspection performed.
Thank you! Jason Gordon Phone #: ###-#### Inspection requested via web by Neal Timmerman
|
Application received | | | 2/6/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 6 2018 11:53AM
|
Plan assigned to (Lee) | 2/6/2018 | | 2/6/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/6/2018 | | FAIL |
|
|
|
Failed prescreen. Need drawings seperated into individual files. Returned to Mike.
|
Plan resubmittals received | | | 2/6/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 2/6/2018 | | 2/6/2018 | | PASS |
Lee G Meredith
|
|
|
Changed to a quick permit due to limited amount of work.
|
PLANS TAKEN FRONT DESK ALARM | | | 2/6/2018 | | DONE |
|
|
|
Quick permit approved with no review comments.
|
Permit Ready to Issue | | | 2/6/2018 | | DONE |
|
|
|
Met
|