Miscellaneous action | | | 7/18/2018 | | DONE |
|
|
|
Per Tim Frost no fees for as builts
|
INSP-Final Inspection | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection complete.
Final Inspection Schindler Elevator interface to Fire Alarm Panel, Randy Burkland on-site contact Phone #: ###-#### Inspection requested via web by Bruce Sullivan
|
INSP-Final Inspection | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PART |
Jim Page
|
|
|
Partial final inspection for fire alarm system complete, hood suppression system interface with fire alarm complete, fire sprinkler interface with alarm complete, audio visual notification complete, monitoring and signal verfication complete, ony item left to inspect is elevator recall and shunt when elevator is complete. TCO for fire alarms authorized for employee training only.
|
Plan Modification Accepted | | | 6/15/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 6/15/2018 | | 6/15/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/15/2018 | | DONE |
|
|
|
Plans approved but as built drawings are still required. Sprinkler heat trace system has been installed but no permit has been submitted or approved. This needs to take place prior to final acceptance. No additional review comments have been provided.
|
Permit Ready to Issue | | | 6/15/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 6/15/2018 | | DONE |
|
|
|
Plan mod
|
INSP-Final Inspection | 6/12/2018 | 6/14/2018 | 6/14/2018 | A | FAIL |
Jim Page
|
|
|
Fire alarm panel model installed does not match what was submitted, issue will need to be resolved before testing/inspection can be performed.
On-Site Contact, Randy Burkland Phone #: ###-#### Inspection requested via web by Bruce Sullivan
|
Miscellaneous action | | | 6/14/2018 | | DONE |
|
|
|
Bruce called to request workflow to be re-opened due to equipment changes.
|
Plan Modification Accepted | | | 6/14/2018 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 6/14/2018 | | 6/14/2018 | | DONE |
Lee G Meredith
|
|
|
|
Plan resubmittals received | | | 3/20/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 3/20/2018 | | 3/20/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/20/2018 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 3/20/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/20/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/8/2018 | | DONE |
|
|
|
Sent back to Bruce. Resubmittal instructions have not been followed. Informed him that corrections must be made before revie can start.
|
Plan assigned to (Lee) | 2/20/2018 | | 2/20/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/20/2018 | | FAIL |
|
|
|
See 1st review comments.
|
Application received | | | 2/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 16 2018 10:26AM
|