INSP-Final Inspection | 10/16/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Jordan Fuger is the contact for this final inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 8/29/2018 | 8/31/2018 | 8/31/2018 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
Please, contact Stacy with time for flush ###-#### Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | CANC |
Troy Cobbley
|
|
|
Scheduled for wrong day.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | CANC |
Troy Cobbley
|
|
|
Scheduled for wrong day.
Underground Hydro Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/14/2018 | 8/15/2018 | 8/15/2018 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line piping is ok for cover.
Underground rough to cover. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/13/2018 | 8/14/2018 | 8/14/2018 | P | FAIL |
Troy Cobbley
|
|
|
Contractor was not done with the install and did not have approved plans or notes. No inspection performed.
Bryan Collins is the contact for this underground rough to cover inspection. He is hoping for an appointment around 2 Pm if that will work. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan Modification Accepted | | | 7/20/2018 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 7/20/2018 | | 7/20/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/20/2018 | | 7/20/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/20/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/20/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/20/2018 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, underground supply approved for cover.
|
Intake Approval | | | 2/20/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/20/2018 | | 2/20/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/20/2018 | | 2/20/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/20/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/20/2018 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 2/20/2018 | | DONE |
|
|
|
|
Application received | | | 2/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 19 2018 7:11AM
|