INSP-Final Inspection | 5/1/2018 | 5/2/2018 | 5/2/2018 | P | PASS |
Jim Page
|
|
|
As builts have been received and completed, final fire alarm ispection complete.
Review of as-built plans as requested by Troy. On site final inspection already completed. Phone #: ###-#### Inspection requested via web by John Siewert
|
Miscellaneous action | | | 4/19/2018 | | DONE |
|
|
|
As built drawings and revised calculations received.
|
INSP-Final Inspection | 4/17/2018 | 4/17/2018 | 4/17/2018 | P | FAIL |
Troy Cobbley
|
|
|
Project can be finaled when as-builts have been received by plan review.
Chris Siewert - Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
INSP-Final Inspection | 4/12/2018 | 4/17/2018 | 4/17/2018 | P | CANC |
Troy Cobbley
|
|
|
Zak Anderson - Technician Phone #: ###-#### >> Inspection requested via web by John Siewert Inspection cancelled from web by: John Siewert
|
Plan assigned to (Lee) | 2/20/2018 | | 2/20/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/20/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 2/20/2018 | | 2/20/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/20/2018 | | DONE |
|
|
|
Quick permit approved. No review comments attached.
|
Permit Ready to Issue | | | 2/20/2018 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 2/20/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/20/2018 | | DONE |
|
|
|
|
Application received | | | 2/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 19 2018 2:23PM
|