Permit Information
Permit NumberFIR18-00138
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 816 W BANNOCK ST
Project NameGarro Bldg 1st Floor TI
Customer Number 
ePlanReviewYes
Description
[Garro Building First Floor TI]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration. Sprinkler work is on 1st floor. System is supplied by a fire pump in the basement.

(No occupancy in tenant spaces is allowed under this permit.)

[BLD17-02285]
his building is sprinklered to allow 5th floor. Permit is for improvements to the shell and core of an existing historic building. Work to include: painting exterior of building, construction of new solid canopy on Bannock Street; demolition of stair connecting 1st floor and basement, remodel of 1st floor exterior entry; new office tenant exterior entry; demolition of interior non-bearing partitions in 1st floor and basement tenant spaces; remodeled electrical, mechanical, and plumbing; and new interior finishes on all floors. Interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. NO OCCUPANCY TO REMODELED TENANT SPACES IS ALLOWED UNDER THIS PERMIT. RELOCTED/FUTURE TENANTS SHALL APPLY FOR PERMIT PRIOR TO OCCUPYING THE SPACE. **JAR**

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/7/20185/8/20185/8/2018APASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.

Phone #: ###-#### Inspection requested via web by Connie Danes
Plan Modification Accepted  4/10/2018 DONE
Sprinkler Plan Check4/10/2018 4/10/2018 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  4/10/2018 DONE
Permit Ready to Issue  4/10/2018 DONE
Plan Mod Approved
DO NOT REISSUE
CHANGE STATUS TO (ISS)  4/10/2018 DONE
INSP-Sprinkler Rough-in3/5/20183/5/20183/5/2018PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler located on level 1, southwest side new corridor complete, approved for cover.
Sprinkler Plan Check2/28/2018 2/28/2018 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  2/28/2018 DONE
DetailsTim Frost
Permit Ready to Issue  2/28/2018 DONE
met
Issue and Print Permit  2/28/2018 DONE
Intake Approval  2/21/2018 PASS
Plan assigned to (Tim)2/21/2018 2/21/2018 DONE
DetailsTim Frost
Sprinkler Plan Check2/21/2018 2/21/2018 FAIL
DetailsTim Frost
1st review completed  2/21/2018 FAIL
DetailsTim Frost
Miscellaneous action  2/21/2018 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  2/20/2018 DONE
Application submitted via PDS Online on Feb 20 2018 1:09PM