INSP-Final Inspection | 3/26/2018 | 3/26/2018 | 3/26/2018 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2018 | 3/2/2018 | 3/2/2018 | A | PASS |
Troy Cobbley
|
|
|
Overhead rough-in passed. Overhead hydro test passed. Piping can be covered
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PART |
Troy Cobbley
|
|
|
Of the two systems the north side passed the overhead hydro. The south side system failed due to visable loss at the guage.
Please call Anthony before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 2/26/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/23/2018 | | 2/23/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/23/2018 | | DONE |
|
|
|
Met
|
Intake Approval | | | 2/22/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/22/2018 | | 2/22/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/22/2018 | | 2/22/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 2/22/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/22/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 2/20/2018 | | DONE |
|
|
|